The Main Avenue South and 26th Street South Assessment Project involves the reconstruction and widening of Main Avenue from 20th Street South to 26th Street South and the construction of 26th Street South in Brookings, SD. This project is crucial for the opening of the Southwest Elementary School and for the future growth of the City of Brookings. Civil Design Inc teamed up with Banner Associates, Inc. to assist the City in fulfilling this project from conception to completion. CDI provided the preliminary and boundary surveys, roadway design, hydraulic modeling and storm sewer design, construction staking, construction observation, and project and contract administration.


Project Facts


Client:
City of Brookings

Location
Brookings, SD

Cost
$3.9 million